Construction Cost
4,135,268.00
Initial Schedule
18 months
Final Schedule
18 months
Key Personnel / Role
Brian Williams - Project Manager
Owner / Contact Information
Lenny Mathews - 757-664-6735
Design Engineer / Contact Information
WRA--Terry Legg - 599-5101
Renovation of Existing Water Booster Pumping Station. Replace Pumps, Motors, electrical, Switch gear, Transformers, etc., Renovate Structure and installation of 3 miles of Marine Cable.
Owner / Project Manager
Norfolk Department of Utilities
Status
Completed