Construction Cost
3,079,000.00
Initial Schedule
12 months
Final Schedule
12 months
Key Personnel / Role
Brian Williams - Project Manager
Owner / Contact Information
David Cooley - 833-1720
Design Engineer / Contact Information
CH2MHill - 873-1511
The Work under this project consists if installation of new 18” RAS header feeding basins, New 42” Primary Effluent Line, Conversion of Two existing Pre-Aeration Tanks into Centrate Equalization Basins.
Owner / Project Manager
HRSD
Status
Completed