Construction Cost
19,775,237.87
Initial Schedule
720 days
Final Schedule
810 days
Final Schedule Reason For Change
Added additional work and change orders
Project Location
Chesterfield Country
Traffic Phasing
On site work with traffic concerns inside plant site
Key Personnel / Role
Frankie Bridgeman - Project Manager
Owner / Contact Information
David Knapp - 1-804-748-1870
Design Engineer / Contact Information
Taylor Turner - Malcom Pirnie - 1-804-740-0181
The project included the installation of 4000 of 30″ DI Sewer Force Main, building a complete solids handling facility, a Methanol Facility, and installation of 3 aeration systems in the aeration tanks. Sewer bypass systems were used, electrical and scada upgrades, structural concrete (3000 CY), and site paving.
Owner / Project Manager
Chesterfield Country
Status
Completed